Relocation of Production and Process Lines – Stages, Costs, and Commissioning
How can you relocate a production line so that, after reassembly, it regains the required production capacity and quality? In the SWENSKA POWERHOUSE guide, we discuss the relocation of assembly, packaging, bottling, and process lines in Poland and across Europe. We explain how to prepare an audit, plan dismantling and transport, re-establish connections, and carry out commissioning and start-up. We also show what data is needed to prepare a quotation and how to establish acceptance terms before halting production.
1. When does the relocation of production lines require detailed planning?
The relocation of a production line requires a detailed plan when restoring operation depends on the interaction of several stations, shared control systems or process parameters. Machines that function properly may fail to achieve their target output after relocation if the way parts are transferred, buffer capacity or utility availability changes. Therefore, the project scope must be established based on the production flow, not solely on the list of equipment to be transported.
Projects involving a change in the layout of the hall, the addition of new machines or the division of an existing line require particular attention. Such changes may affect the sequence of operations, control systems and safeguards. Their consequences should be identified before the schedule is approved, since additional design work is difficult to fit into downtime originally intended only for dismantling and assembly.
The plan should specify when production will stop, the conditions for starting the work and the date when the line must be ready for testing. Time is also needed to remove faults revealed during commissioning. The date when the last machine is positioned in the hall is not yet the date when commercial production will resume.
2. How does the relocation of a production line differ from moving a single machine?
For a single machine, the scope of checks focuses on its operation and connections to its surroundings. In a line, there are additional dependencies between stations: product transfer, exchange of ready signals, responses to stoppages and the flow of quality data. Acceptance of individual devices does not yet confirm that the entire system is operating correctly.
For example, in a hypothetical packaging line, a machine may achieve the target number of cycles while production is still interrupted by an insufficient buffer before the palletizer. Simply increasing the conveyor speed will not solve the problem if the next station does not receive packages at the appropriate rate.
Relocation documentation must therefore cover both the equipment and its interconnections. This also applies to PLC software, HMI panels, robots, vision systems and product identification devices. It is necessary to know where the recipe is stored, which station controls the flow and how the line behaves when a cycle is interrupted.
3. Relocation of a complete line, part of a line, a line module and a process train
The scope of the relocation should define the physical and functional boundaries of the work. The terms “line”, “module” and “process train” are sometimes used differently, so the documentation should assign specific equipment, installations and connections to each of them.
| Project scope | What it includes | What must be determined before dismantling |
|---|---|---|
| Complete line | Interconnected machines, inter-operation transport, control systems and auxiliary equipment | Whether all installations required for operation are being relocated or whether some must be recreated at the new plant |
| Part of a line | Selected stations or a section of the process | How both parts will operate and be secured after separation |
| Line module | A separate unit, e.g. dosing, quality control or palletizing | What mechanical connections, signals and parameters are needed for its reintegration |
| Process train | Equipment performing successive process operations, together with the connecting installations | How to recreate the process conditions, flows, tightness and cooperation between devices |
When moving part of a line, shared equipment must be taken into account. A control cabinet, cooling system or extraction system may also serve machines remaining at the plant. Disconnecting such an installation requires a solution for both locations to be agreed in advance.
4. What types of production and process lines are most often relocated?
Relocation may involve assembly, packaging, filling, dosing, palletizing, welding, machining, painting and plastics-processing lines. However, the preparation method is determined by the process flow and the design of the equipment, not by the industry name alone.
In discrete manufacturing, where successive stations process or assemble individual parts, product transfer points, tooling and cycle synchronization are important. In continuous processes, the routing of installations, stabilization of temperature, flow or pressure, and the method of stopping and restarting the process become more significant.
A line made up of independent modules may allow larger assemblies to be transported. A highly integrated structure may require more extensive dismantling and the recreation of connections. This choice affects both transport dimensions and the amount of assembly work, so it should be agreed jointly by the people responsible for the process, transport and commissioning.
5. Audit before relocating a production line
It is worth carrying out the audit while the line is still producing. This makes it possible to observe the actual cycle, stoppages, material flow and operation of auxiliary equipment. A review of the documentation alone after the power has been disconnected will not show which settings operators adjust during operation or where bottlenecks occur.
The audit results should provide a reference point for later acceptance. The achieved output and quality should be recorded together with the measurement conditions: product, recipe, staffing and observation time. Known faults must be distinguished from changes whose removal or implementation falls within the relocation scope.
Audit checklist before relocating a production line
| Area | What to check | Decision resulting from the findings |
|---|---|---|
| Documentation | Whether instructions, diagrams and plans match the actual configuration | What deficiencies must be completed before disconnecting the line |
| Automation | Availability of projects, backups, service tools and access permissions | Whether the involvement of the manufacturer or integrator will be required |
| Utilities | Supply parameters and demand during operation, including shared installations | How to prepare connections in the target hall |
| Transport | Weights, dimensions, centre of gravity, lifting points and removal routes | Where to divide the line and how to select the equipment |
| New layout | Material flow, service access, operating zones and safeguards | Which changes require a design before assembly begins |
| Process and risks | Baseline condition, known faults, downtime limitations and acceptance requirements | What must be confirmed during testing after the relocation |
The audit should result in a list of actions with assigned people and deadlines. Establishing that a controller project is missing is useful only when it is known who will obtain it and whether it will be available before production stops.
6. Inventory of the line before relocation
The inventory determines what is actually to be moved to the new location. In addition to the main machines, it includes conveyors, cabinets, platforms, guards, units, auxiliary installations and equipment needed for changeovers. Each item should receive an identifier linked to the layout plan and photographic documentation.
Tooling should be listed separately: holders, gauges, format parts, nozzles, guides and special tools. Assigning them to a product or station makes test preparation easier. The absence of a small component may prevent a particular production variant from being commissioned despite the completeness of the main machines.
The register should distinguish between items being moved, items remaining on site and items intended for replacement. Packing lists are prepared on this basis. Grouping equipment by station and assembly sequence makes it possible to deliver the required parts without searching through crates containing the entire line.
7. Marking, labelling and mapping connections
Connections should be described before they are disconnected. The marking should make it possible to clearly identify both ends of a cable, hose or installation section and locate them on the diagram. A number written on a loose label is of little help if it is not known which device it belongs to.
Photographs supplement the connection map, especially when diagrams are out of date, but they do not replace it. The routing, the settings of adjustable components and the way cables are routed around moving parts must also be recorded.
Minimum standard for marking connections
The following set can be adopted as the project’s organizational standard and extended as appropriate to the line design.
| Documentation element | Scope | Application during assembly |
|---|---|---|
| Labels | Permanent, matching markings on both sides of the disconnected connection | Identification of the correct connection points |
| Photographs | General views and close-ups with clear identifiers | Recreating the position and routing of connections |
| Connection map | Source and target device, terminals or ports, function and reference to the diagram | Checking connection correctness and clarifying discrepancies |
| Digital archive | Projects, configurations and backups identified by version, date and device | Comparing configurations and preparing possible system restoration |
When archiving, it is necessary to check what the backup actually contains. Reading data from a controller does not always provide a complete project that can be edited. The availability of the correct software and licences must be confirmed before dismantling.
8. Dismantling a production line in stages
The dismantling sequence follows from the design of the equipment, installation dependencies and the subsequent assembly plan. Tasks requiring power, such as positioning mechanisms for transport or emptying an installation in the mode specified by the manufacturer, must be taken into account before the relevant energy sources are disconnected.
Before interfering with hazardous areas, the agreed procedure for disconnecting, preventing reconnection and verifying a safe state must be applied. Auxiliary power supplies and energy remaining in the system must also be taken into account, such as pressure, heated components or raised assemblies. In Poland, requirements for disconnecting machines from energy sources are set out, among other provisions, in § 18 of the regulation on the use of machinery by employees. The prevention of unexpected start-up is addressed by ISO 14118:2017.
After separating a module, it is worth confirming its completeness, marking and readiness for lifting. This checkpoint helps identify missing components before the package is closed and the work area is released.
If part of the plant continues production, the plan must define the boundaries of the work and how shared installations will be secured. The possibility of maintaining production cannot be assumed without checking these dependencies.
9. Securing line components for transport
Transport protection should protect the geometry of the assembly, its surfaces and sensitive components. Long frames, conveyors and structures require an assessment of how they will be supported. Improper lifting can deform an assembly before loading, so lifting points and the necessary reinforcements should be determined based on the documentation and an assessment of the structure.
Guides, sensors, cameras, displays and projecting connections require separate preparation. Moving parts should be secured in accordance with the manufacturer’s recommendations, while disconnected installations should be protected against contamination. The type of packaging should take into account the route, transshipments, storage time and permissible environmental conditions.
Protecting the equipment from damage and securing the load to the vehicle are two related tasks. A crate or film alone does not ensure stability during braking or turning. Practical principles for preparing and securing transport are described in the European Commission guidelines on cargo securing.
10. Transporting production and process line components
Transport should be planned according to the sequence in which components are needed for assembly. The first vehicle should deliver the assemblies that can be positioned immediately, together with the required supports and fastening elements. Transporting all modules at once may hinder the work if the hall has no room to store them safely.
Vehicle selection requires data on the weight, dimensions and distribution of the load. Exceeding permissible parameters is assessed for the vehicle or vehicle combination, taking the load and axle loads into account. The GDDKiA information on abnormal transport presents the principles for organizing such journeys. A large module should be assessed in advance for possible division and the consequences of that division for reassembly.
The route does not end at the plant gate. The unloading area, surface load-bearing capacity, passage dimensions, manoeuvring space and route to the foundation must be checked. Issues concerning heavy assemblies are discussed in more detail in the article on the relocation of heavy and oversized machinery.
11. Relocating a line with conveyors, robots and automation
For conveyors, the product transfer heights, the position of guides, sensors and stops must be recreated. The operation of the control system is equally important: the preceding station should respond correctly when there is no space in the next section, and the line should maintain the correct product sequence after a stoppage.
After moving a robot, the actual geometry of the station must be checked against the data used by the program. A change in the position of a fixture, conveyor or base may require adjustments and repeated tests. With regard to standards, it is necessary to distinguish the requirements for the robot itself, described in ISO 10218-1:2025, from the requirements for applications and integration covered by ISO 10218-2:2025. Details are discussed in the publication on the relocation of robotic workstations.
In quality-control systems, the entire decision path must be checked: product recognition, assignment of the result, signal transmission and rejection of the correct item. A correct camera reading is not enough if, after the conveyor length changes, the reject mechanism responds to a different product.
12. Relocating assembly, packaging, filling, dosing and palletizing lines
In an assembly line, the relationship between tooling, recipes and in-process inspection must be maintained. Tests should cover the agreed product variants, particularly when they use different holders, tools or assembly parameters. Commissioning one variant does not confirm the readiness of all changeovers.
In a packaging line, packaging formats, product guidance and cooperation between the packer, labeller and end-of-line equipment are important. A test using substitute packaging may help with mechanical adjustment, but the acceptance conditions should specify the target materials and the requirements concerning closure, labelling and packaging appearance.
For filling and dosing, the product supply conditions must be recreated, tightness must be checked and dosing accuracy must be verified under the agreed conditions. If the process is subject to hygiene requirements, the scope of work should also include appropriate cleaning and confirmation that the installation is ready for contact with the product.
For palletizing, acceptance should take into account the availability of empty pallets, the stability of the product arrangement and the removal of finished units. A change in the hall’s logistics may limit the output of this part of the line even when the robot or palletizer is completing its cycle correctly.
13. Relocating welding, machining, painting, injection-moulding, forming and extrusion lines
In a welding line, fixture geometry, part clamping, process power supply and extraction are important. Tests after assembly should confirm the required product characteristics and joint quality according to the criteria applicable to the production in question. Merely executing the motion program does not determine welding quality.
A machining line requires checking the foundation, geometry and cooperation with part transport. The relocation scope must include coolant systems, filtration and chip removal if they are necessary for operation. Omitting them from the plan may make loaded testing impossible.
For painting, ventilation, surface preparation and coating curing conditions are important. If the substances or dust used may create an explosive atmosphere, the new configuration must be taken into account in the risk assessment and explosion-protection documentation. The obligations in this area are set out in the Regulation of the Minister of Economy of 8 July 2010.
In injection-moulding, forming and extrusion lines, the process also depends on auxiliary equipment: dryers, feeders, thermostats, cooling systems, take-off units and cutting systems. The start-up plan should include stabilization of the parameters of the entire train and product inspection after the agreed operating conditions have been reached.
14. Assembling the line according to the new layout
The new layout should be checked for material flow, operation, servicing and safety before assembly begins. Space must be left for opening cabinets, changing tools, removing jams and transporting parts. The machine outline on a plan does not show the entire area required for its operation.
The positioning of assemblies should be based on agreed reference points and the manufacturers’ requirements. Checking the position of successive sections helps avoid a situation in which small deviations at the beginning of the line make it impossible to connect its end. The anchoring and foundation method must correspond to the equipment and the conditions in the new hall.
At the same time, the effects of the changes on safety and compliance must be assessed. Merely moving an existing line does not determine whether a new conformity assessment and CE marking are required. Relevant factors include changes to the function, integration and safeguards, as well as whether the work results in what is effectively a new machine or new assembly. The legal context is explained by the European Commission in its information on machinery legislation.
In October 2026, the primary act governing the placing of machinery on the market or putting it into service remains Directive 2006/42/EC. Regulation (EU) 2023/1230 will generally apply from 20 January 2027; it defines a substantial modification and specifies the obligations of the entity carrying it out. For projects involving rebuilding, the scope and applicable legislation must be assessed rather than determining obligations solely by the transport date. Details are provided in Articles 3(16), 18 and 54 of the Regulation.
15. Connecting utilities to the production line
Hall readiness means that utilities with the required parameters are available at the connection points. It is necessary to check not only the presence of electricity, compressed air or cooling, but also their capacity during the simultaneous operation of consumers. Measuring pressure with the installation stopped does not show how it will behave at full demand.
For each utility, the required parameters, connection method and responsibility boundaries should be established. This also applies to extraction systems, drains and return installations. The schedule should include a date for confirming the readiness of these installations before equipment testing begins.
Electrical work requires checks appropriate to the scope of the installation and the changes made. The standard concerning the electrical equipment of machines and groups of machines operating in a coordinated manner is IEC 60204-1:2016 together with amendment AMD1:2021. The configuration of the industrial network and connections to plant systems must be agreed separately so that the stations can exchange the required data.
16. Commissioning the production line after relocation
Commissioning begins by confirming the assembly, installation and organizational readiness for individual tests. This includes checking connections and safeguards, removing transport locks at the designated stage and preparing work areas. The test sequence must correspond to the line design and the equipment instructions.
Automation specialists compare the configuration with the approved baseline. A backup is used to restore the system when necessary; it should not be automatically loaded into a correctly functioning controller. Every change to the program or parameters must be recorded so that the version being tested is known during the trials.
Tests cover input and output signals, controlled movements, communication between stations and responses to disturbances. Progress to the next stage should depend on the results of the previous one. Automatic tests may begin once the safety conditions required for that mode have been confirmed.
At the level of the entire line, stopping, restarting the cycle and handling products remaining between operations must also be checked. This makes it possible to identify errors that are not revealed by a single uninterrupted passage of a part.
17. Process start-up of the production line
Process start-up is intended to confirm that the line produces a product with the required characteristics under the agreed conditions. Depending on the process, it includes parameter stabilization, station adjustment, production of trial batches and assessment of the results. Operators, process engineers and quality personnel are needed at this stage.
Output must be defined in a way that corresponds to the purpose of acceptance. The number of machine cycles, the number of all items produced and the number of conforming products are different quantities. The test conditions should specify which of them is being assessed, for how long and how stoppages and rejects are taken into account.
Comparison with the condition before relocation requires conditions that are as consistent as possible: material, recipe, tools and measurement method. If the product or technology was also changed, the result must be interpreted taking those changes into account. Relocation does not automatically remove the line’s previous limitations; their modernization should be agreed separately.
After adjustment is complete, it is worth recording the approved settings and operating conditions. This gives the next production shift a defined starting point.
18. Production tests, line acceptance and final documentation
Acceptance conditions should be agreed before dismantling. They should specify the products and variants covered by the tests, quality criteria, expected output, observation time and the method of documenting the results. It must also be established who provides the material, operators, tooling and measurements.
Production acceptance does not replace safety checks. In Poland, when safe use depends on installation conditions, a machine is subject to inspection after installation at another place of use. This requirement follows from § 26 of the regulation on the use of machinery by employees.
The scope of checks for safety-related control systems should result from the risk assessment, the design and the changes introduced. ISO 13849-1:2023 concerns the design of such parts of control systems; it does not assign one required performance level to all functions of every line.
The final documentation should reflect the post-assembly condition: equipment layout, diagrams, configurations, approved program backups and the results of inspections and tests. The acceptance report must distinguish confirmed results from work that remains to be completed. For each open item, responsibility, deadline and impact on the possibility of using the line must be specified.
19. How can downtime be reduced when relocating a production line?
Downtime can be reduced by carrying out possible work before the production stoppage. This includes preparing the hall, installing connections, prefabricating agreed sections of the installations and assembling the required parts. The condition is that the data on which this work is based must be approved in advance.
The schedule should identify the tasks that determine the date of the restart. An additional assembly team will not help if the next stage is waiting for a connection, a controls specialist or material for testing. The availability of these resources must be confirmed for specific dates, including when the work falls on a weekend.
Some automation preparation can be carried out away from the line. Examples include robot programming and simulation tools described in the ABB RobotStudio materials. The usefulness of a simulation depends on the model matching the installation; its result does not replace testing the actual station.
Phased relocation makes sense when the remaining part of production can operate independently and safely. If the stations use shared control systems or utilities, preparing such a division may require additional work.
20. What determines the cost of relocating a production line?
The cost results from the scope of dismantling and restoring the line, transport conditions, required changes and the expected level of commissioning. A small line with undocumented controls may require a significant amount of work even though it fits on several standard vehicles.
Offers should be compared according to the same stages: preparation, dismantling, securing, transport, assembly, connections, automation, checks and production tests. It should be established whether the price includes installation materials, new cables, the involvement of manufacturers and the removal of previously identified faults.
Data needed to price the relocation of a production line
| Document or information | Significance for pricing |
|---|---|
| Current and target layouts | Allows the routes for moving equipment, the scope of assembly and required changes to be assessed |
| List of machines, modules and auxiliary equipment | Defines the work boundaries and makes it possible to check that the scope is complete |
| Dimensions, weights, centre of gravity and lifting points | Provide the basis for selecting equipment and vehicles |
| Electrical diagrams and automation documentation | Help assess the scope of disconnections, installation restoration and integration |
| List of utilities with parameters | Enables connection work and the division of responsibilities to be determined |
| Information on projects, backups and service access | Helps identify the need for manufacturer involvement or documentation recovery |
| Photographs of the line, passages and loading areas | Show access and work-organization limitations |
| Downtime date and available working hours | Affect staffing, shift patterns and the sequence of activities |
| Quality, output and acceptance criteria | Define the scope of start-up and the time and resources needed for testing |
| Addresses, transport conditions and delivery dates | Make it possible to assess the route, transshipments, permits and possible storage |
If some data is missing, the offer should state the assumptions made and the scope requiring further investigation. The plant budget should separately include the cost of limiting production, trial materials and the work of the in-house team. These are not always part of the relocation contractor’s remuneration.
21. Relocating a production line from Germany to Poland and industrial relocations in Europe
When relocating from Germany to Poland, the readiness of both plants must be coordinated. At the source site, access to the equipment and documentation, the production completion date and the possibility of using the loading infrastructure are important. At the destination site, the preparation of the hall, connections and space for deliveries are key.
The date by which the old hall must be vacated may be earlier than the readiness of the new one. In that case, the project must include storage, protection of the equipment during that period and additional transshipments. These activities should be included in the scope and schedule before transport is ordered.
The transport of goods with Union status between Germany and Poland takes place within the EU customs union, without internal customs duties. It should not be equated with imports from outside the customs union, such as from Ukraine, which require separate formal preparation. The principles of the free movement of goods are explained by the Council of the EU in its description of the customs union.
Regardless of the direction, transport requirements along the entire route, the rules for the teams working at both plants and responsibility for handing equipment over between stages must be agreed. The arrangements should be available to all contractors involved.
22. A company for relocating production lines — how to choose a contractor?
A contractor should be assessed based on the proposed method of execution and documented experience relevant to the project scope. A reference concerning the transport of a machine does not yet confirm competence in control-system integration or process start-up. These areas require specific people or partners to be identified.
The offer should explain who is responsible for installations, automation, safety checks and production tests, and which tasks remain the plant’s responsibility. The term “turnkey” does not replace such a division. The procedure to follow if a documentation discrepancy or the need to replace a part is revealed during dismantling is equally important.
Before making a selection, schedules, pricing assumptions and acceptance conditions should be compared. It is also worth checking the scope of insurance for the work and transport. Responsibility for coordination should be unambiguous, including when individual tasks are carried out by several companies.
23. How can SWENSKA POWERHOUSE help with the relocation of a production line?
SWENSKA POWERHOUSE supports the preparation and execution of production and process line relocations. The agreed scope may include auditing, inventory, schedule development, dismantling, equipment protection, transport organization, unloading, moving equipment into the hall, assembly, utility connections, commissioning and start-up support.
Projects may involve moving a line within a plant, between locations in Poland or internationally. Preparation begins by defining the work boundaries and the expected condition of the line after relocation. On this basis, the tasks of SWENSKA POWERHOUSE, the client’s team, equipment manufacturers and other contractors can be agreed and their work linked to the production restart date.
Frequently asked questions (FAQ)
How to relocate a production line step by step?
Relocation is planned from checking the operating line through confirming its parameters after installation. The subsequent stages include:
- an audit, determining the scope of the relocation, and agreeing on acceptance criteria;
- preparing the target facility, documentation, data backups, and markings;
- safe shutdown, securing energy sources, and dismantling the agreed assemblies;
- packing, transport, and deliveries in the order required for installation;
- positioning, connecting, and carrying out staged checks of the equipment, controls, and safety systems;
- technological start-up, production trials, and acceptance.
If safe operation depends on the installation conditions, after installation in the new location, the inspection specified in § 26 of the regulation concerning the use of machinery by workers is required. Performance tests do not replace it.
How long does it take to relocate a production line?
The timeline depends on the scope of dismantling, the readiness of the new facility, and the work required to resume production. The schedule is affected by dependencies between tasks: installation may have to wait for the foundations, while commissioning may depend on automation, utilities, or material for testing. The duration of preparation, downtime, and ramp-up to the agreed output must be determined separately. The machine delivery date alone does not determine when production will resume.
Does relocating a production line require production to be halted?
The section being relocated must be shut down for the duration of work requiring its disconnection and dismantling. The remaining part of the plant may continue production if it retains the necessary utilities, controls and safeguards and is separated from the work area. The possibility of staging the work should be assessed at the level of the entire process. A stock of semi-finished products may keep downstream workstations running, but it will not resolve the issue of a shared control cabinet, cooling system or extraction system.
How do you prepare a production line for relocation?
Preparation should begin while the line is still operating. This makes it possible to record its performance, product quality, recipes, and known faults under defined production conditions. The documentation must then be verified against the installation, auxiliary equipment assembled, data secured, and connections labeled. Before shutdown, the boundaries of disassembly, the readiness of the destination site, and the resources required for commissioning—automation specialists, operators, materials, and tools—should also be agreed upon. The removal of existing faults or modernization should be clearly included in the scope of work.
How should line elements be marked before disassembly?
Each module should be assigned an identifier linked to the layout plan, photographs, and packing list. Disconnected cables and hoses should be labeled at both ends, with references to the appropriate terminals, ports, or connections. The connection map should also indicate their function. Sensors, holders, format parts, and small accessories must be assigned separately to the relevant stations. Photographs help recreate the installation process, but they do not replace unambiguous labeling.
When relocating a line, do you need to back up the PLC, HMI, and robots?
Yes. Before disassembly, the current programs, configurations, recipes, and parameters of the devices making up the line must be secured. The copies should be labeled with the date, version, and device identifier and stored separately from the equipment being transported. You should also confirm the availability of the tools, licenses, and permissions required to restore them.
The scope of the copies depends on the method used. Siemens distinguishes, for S7 controllers, between a backup for restoration and data that enables project editing. If the relocation requires changes to the control system, a restoration backup alone may not be sufficient. After installation, the correct configuration should not be automatically overwritten with an older copy.
When does transporting production lines require oversize transport permits?
In Poland, a permit for the movement of an abnormal-load vehicle is generally required when the transport combination exceeds the permitted dimensions, actual gross vehicle weight, or axle loads. The vehicle’s parameters together with the load are assessed, not the line module alone. The rules and permit categories are presented by the GDDKiA. Vehicle selection, the arrangement of components, and the possibility of dividing the module must be considered before ordering transport. For an international route, the requirements are determined for each country along the route.
Can changing the layout after relocation affect CE compliance and line conformity?
Yes, if the new layout changes access to hazardous areas, the operation of safeguards, control systems, or the interaction between machines. The effects of these changes must be assessed, and the documentation and inspections updated accordingly. However, simply relocating an existing line does not automatically mean that a new conformity assessment is required. If the modification results in what is effectively a new machine or new assembly, manufacturer obligations may arise. The principles for assessing modified products are discussed in the European Commission’s “Blue Guide,” section 2.1.
The applicable legal framework is also relevant. Regulation (EU) 2023/1230 will generally apply from 20 January 2027; before then, Directive 2006/42/EC remains the main basis for requirements applicable to new machinery. The European Commission explains the timing and scope of application of the regulations here.
How can downtime be minimized when relocating a production line?
Most preparatory work should be completed before production is stopped: install the connections, prepare the foundations, approve the hall layout, and gather the parts. Deliveries should follow the assembly sequence, while the schedules of automation technicians and service teams should be tied to the actual readiness of the workstations. The schedule should also reserve operators, materials, and acceptance testing. An additional team will not shorten the downtime if commissioning is waiting for a missing utility or a control-related decision.
What information is needed to quote the relocation of a production line?
For the quotation, a description of the line and the expected scope of work after its setup are required. It is worth preparing:
- a list of machines, modules, and auxiliary equipment, including their weights, dimensions, and photographs;
- the current and target layout, along with information about access, internal routes, and loading areas;
- mechanical, electrical, and automation documentation, utility requirements, and the status of program backups;
- the addresses of both locations, the shutdown date, the permissible downtime, and the available working hours;
- planned changes and acceptance criteria for the quality, efficiency, and operation of the entire line.
Any missing data should be identified as an item to be determined during the audit so that the offer clearly distinguishes the confirmed scope from the assumptions made.
How much does it cost to relocate a production line?
The cost can be determined once the scope of dismantling, transport, and recommissioning of the line has been established. The price is influenced by the weight of the equipment, the number of connections, the state of the documentation, the changes required, and the scope of commissioning. A small line with undocumented control systems may require substantial automation work. When comparing offers, check whether they include connections, installation materials, service support, and production trials. The cost of lost production and the work of your own team should be included separately in the plant’s budget.
Can only the production line module be relocated?
Yes, provided it can operate at the new location and the part remaining at the plant can be operated safely. The shared control system, safety functions, utilities, and signals exchanged with adjacent workstations must be checked. Mechanically disconnecting the module does not determine whether it can operate independently. If it uses a shared control cabinet or installation, the project may require additional equipment and software changes. The scope of this work should be determined before dismantling.
What does turnkey production line relocation include?
It may include project preparation, dismantling, securing, transport, installation, connections, commissioning and start-up completed with the agreed acceptance. However, the term “turnkey” requires clarification in the contract. It should specify who prepares the hall, carries out the automation and safety checks, supplies the material for testing and approves the results. The final documentation and the procedure for handling defects should also be defined so that the handover of configured machines is not confused with achieving the required production parameters.
What are the most common mistakes when relocating production lines?
Particularly costly are errors that only come to light during recommissioning:
- failure to record the parameters from before disassembly, making it difficult to assess whether performance and quality have been restored;
- overlooking shared installations, which, once disconnected, also prevent machines remaining at the plant from operating;
- confirming utilities without taking into account the simultaneous demand of the entire line;
- accepting individual devices without checking product transfer, stopping, and restarting the cycle of the entire system.
The test plan should take these interdependencies into account and identify the people responsible for resolving non-conformities.
Company for relocating production lines — how to choose a contractor?
The contractor should be evaluated based on the scope for which they actually assume responsibility and on references for comparable work. For a project involving commissioning, they should identify the individuals or partners responsible for automation, utilities, safety, and technology. The offer must include a schedule, a division of tasks with the plant, and measurable acceptance criteria. It is also worth checking the scope of insurance coverage and how changes identified during the work will be accounted for. When several contractors are involved, a clearly designated coordinator is essential.
Sources and basis of the article
- Use of machinery by employees – Regulation of 30 October 2002.
- ISO 14118:2017 - prevention of unexpected start-up
- European Commission – securing loads in road transport
- GDDKiA - organization of abnormal transport
- ISO 10218-1:2025 - safety of robots and applications
- ISO 10218-2:2025 – robot and application safety
- Protection against explosive atmospheres in the workplace – Regulation of 8 July 2010
- European Commission – machinery regulations
- Regulation (EU) 2023/1230 on machinery
- IEC 60204-1:2016 + AMD1:2021 - electrical equipment of machinery
- ISO 13849-1:2023 – safety-related parts of control systems
- ABB – robot programming and simulation
- EU Council – customs union rules
Legal notice and disclaimer
Publications available on the SWENSKA POWERHOUSE website, including articles, guides, expert materials, project descriptions and case studies, are general, informational and educational in nature. They do not constitute legal, technical, design or health and safety advice, nor instructions for carrying out a specific transport, relocation, loading, unloading, assembly, dismantling or other logistics project.
Publication content is prepared on the basis of the information and knowledge available at the time of writing. Despite due care, it may contain simplifications, may not take into account every circumstance of a specific case, or may become outdated, in particular as a result of changes in legislation, administrative requirements, technical conditions or organisational circumstances.
Every transport, relocation, machinery delivery, loading, unloading, assembly, dismantling or other logistics project requires an individual analysis taking into account, in particular, the actual parameters and properties of the load, technical documentation, the route, place of execution, required formalities, current regulations, and technical and organisational conditions.
Publication content should not be the sole basis for decisions or actions concerning a specific project. Before using it, the user should verify that it is current and suitable for the particular case and, where required, obtain an appropriate specialist analysis.
Unless expressly stated otherwise, publications do not constitute an offer within the meaning of the applicable provisions of the Polish Civil Code, a commitment to provide a specific service, or any assurance or guarantee that particular parameters, deadlines, costs, permits or results will be achieved. The terms of a specific service are always set out in the relevant documents for that order.
The user uses the information contained in the publications at their own risk. SWENSKA POWERHOUSE is not liable for the consequences of decisions or actions taken solely on the basis of publication content without an analysis appropriate to the specific case, subject to any liability that cannot be excluded or limited under mandatory provisions of law.